The first question on a site visit is what the covering is made of, how old it is, and where the structural members sit beneath it. Square metres describe a boundary; they do not establish what can be fixed safely, what will generate through the year, or what an installer can reach for maintenance in later years. Starting with the area puts the drawing ahead of the building, and that order is difficult to undo once racking has been ordered.
Added dead load from an array is usually modest but rarely uniform. Ballasted systems concentrate weight in trays and walkways; penetrating systems transfer load through fixings into purlins and rails. Both interact with the covering, in different places and with different consequences. The survey records the roof type, the condition of the membrane or sheeting, previous repairs, ponding, corrosion around services and any history of leakage. A roof approaching the end of its covering life changes the programme, because replacing a membrane around a live array requires removal and reinstatement of the racking. That decision belongs at the beginning of the project, not in a variation issued after commissioning.
Structure before geometry
Load path, member capacity and covering condition set the envelope for the array. Concentrated ballast may be acceptable directly over a beam and unacceptable between two members; a fixing into sheeting achieves little if the purlin below cannot carry it. Remaining service life belongs in the same calculation, because most arrays will outlive at least one roof covering. The structural review therefore precedes the layout: the engineer's findings define where rows may sit, where they may not, and what strengthening, if any, would be required before installation.
Preserving the roof warranty
Penetrations, construction traffic and cable routes can all affect a manufacturer's warranty terms. The permitted fixing method is confirmed with the owner and the roof supplier before design, and confirmed in writing. A verbal assurance from a supplier cannot be relied on years later when a leak claim is made. Where the warranty requires an approved installer, a specific flashing detail or a protective layer under ballast trays, those requirements are written into the specification and checked at completion.
Shade by hour, not by percentage
An annual shade figure hides the useful information. What matters is when the losses fall and whether they coincide with the site's demand window. Plant, exhaust stacks, parapets, neighbouring buildings and the array itself all cast shade that moves with the season. The shading study should output an hourly profile for representative days in each season, set against the load profile. A roof with modest annual shade loss may still perform poorly if the losses fall in the late afternoon, when the business is buying grid energy at its most expensive. Morning shade on a site that starts its day later can be largely irrelevant. That comparison decides row spacing and orientation as much as raw yield does.
Drainage after racking
Panels and walkways change how water moves across a roof. A detail that was acceptable on a bare membrane can impound water once a row of modules slows runoff or a cable tray bridges a fall. Ponding adds load exactly where the structure may already be working hardest, and standing water accelerates covering failure. Outlet positions, overflow paths and falls are reviewed before finalising row spacing, and a check is made that maintenance staff can still clear a blocked drain. After installation, water must be able to leave the roof by the route it used before.
Access reduces usable area
Setbacks, safe routes to switchboards and mechanical plant, and room to isolate or replace a single module all reduce the panel count. These reductions are legitimate: a layout that cannot be maintained will not keep generating. Cable routes and fixings need to align with drainage falls and with the paths maintenance staff use to reach plant. A layout that blocks access to an air handling unit must be revised regardless of how completely it fills the plan. Fire and emergency access requirements vary by jurisdiction and building class, so the applicable rules are confirmed with the certifier rather than taken from a generic diagram.
Two professional opinions, not one
A roof assessment draws on two distinct disciplines. A structural engineer determines whether the members below the covering can carry the added load and transfer it safely into the building frame. A roof supplier understands the covering system: the membrane or sheet, its fixings, its seams and the terms under which its warranty remains valid. Neither can substitute for the other. An engineer may approve a load that a manufacturer will not permit to be penetrated; a supplier may accept a fixing detail that the purlins cannot support. Both views are obtained before the array geometry is fixed, and any disagreement is recorded rather than settled by choosing the more convenient answer.
Ballasted and penetrating fixings in Australian conditions
Ballasted systems avoid holes in the membrane, which suits a strict warranty or a new covering, but they place concentrated dead load on the structure and must resist wind uplift without relying on the roof's own weight alone. High wind regions, cyclonic design areas and exposed coastal sites require uplift calculations that treat ballast as one variable among several. Penetrating systems anchor into the structure and generally use less material, yet every penetration is a potential leak path and a point the roof supplier will want detailed. On metal sheeting the fixing must land over a purlin or into an approved rail; on a membrane roof it must be sealed to the manufacturer's detail. The two approaches are compared on the specific roof, with the wind rating and the warranty terms in the same document.
Membrane compatibility and the written record
Compatibility is a documented question, not a visual one. Some membranes react with the plastics in cable ties, separators or adhesives used by racking systems; others require a protective layer wherever a ballast tray or walkway sits. The manufacturer's written position is obtained on the proposed attachment, the permitted traffic routes and any required protection mat, then reflected in the warranty documentation. Where the roof is near the end of its covering life, the sequence is set out explicitly, including who removes and reinstates racking if the membrane is replaced during the system's life. Settling that question before installation produces a schedule; discovering it during year six produces a dispute.
What actually sets the size
Once the usable roof is defined, sizing depends on interval demand: when load occurs, how steady it is, and how much generation can be consumed on site as it is produced. A large roof above an empty building is not the same opportunity as a smaller roof over a continuous process. The two shapes are compared before capacity is recommended, especially where export is constrained and surplus has nowhere to go. The relevant comparison is between the generation profile and the consumption profile at the same hours, not between roof area and an annual electricity total.
The content of a useful roof report
A report worth acting on states its assumptions. It identifies the roof construction, the condition of the covering, the location of structural members and the remaining service life; records the wind classification and the proposed fixing detail; sets out the manufacturer's written position; describes shade and drainage findings with their periods; and shows the access routes that have been preserved. It also names the data the assessor did not have, so that gaps are visible rather than filled by assumption. Such a report is the basis of the design, not a document filed after the fact.
When the roof is unsuitable
There are roofs on which solar should not be built. A covering already failing, a structure that cannot take concentrated load without extensive strengthening, a warranty that cannot be preserved, or a shading pattern that removes generation exactly when it is needed can each make the proposition weak. Identifying these conditions early is cheaper than discovering them during commissioning. Where the roof is unsuitable, the alternatives are examined on their merits: a carport, a ground mount on available land, or a different building in the same portfolio. Each alternative carries its own structural, connection and access questions, and is assessed by the same method.
How much additional load does a rooftop array impose?
The distributed dead load of a typical framed array on metal sheeting is modest, but the governing figures are the concentrated loads: ballast trays, walkways and fixing points. The structural engineer calculates the load path from each fixing into the purlins, rails and frame, and checks the roof against the applicable wind actions for the site's region. The answer for a specific building comes from that calculation, not from a generic figure per square metre.
Will installing solar void the roof warranty?
It can, if the fixing method, traffic routes or materials conflict with the manufacturer's terms. The permitted attachment detail is confirmed in writing with the roof supplier before design, including any required protection layers and approved installers. Where the warranty cannot be preserved on the proposed system, either the fixing approach changes or the roof is renewed first; proceeding without written confirmation transfers the risk to the owner.
Should an ageing roof be replaced before the array is installed?
Where the covering's remaining service life is shorter than the intended life of the array, replacement before installation is usually the lower-cost sequence, because removing and reinstating racking around a membrane renewal adds labour, crane time and disruption. The survey estimates remaining life from the covering type, condition and repair history, and the comparison is made explicitly in the programme rather than deferred to a later variation.
What records are needed to start a roof assessment?
Roof plans or structural drawings, the covering manufacturer's warranty documents, a recent electricity bill and a description of operating hours are enough to begin. The assessor identifies which additional records — purlin spacing, wind classification, drainage details, plant locations — would change the conclusion, so the owner is not asked to collect material with no bearing on the outcome.
Roof questions
Structure, warranty and shade.
Three questions that follow from the note.
What structural evidence is required before an array is designed?
A certification from a qualified structural engineer covering the roof's capacity, the proposed load and the fixing method. The design is conditional on that certification, and the scope records it as a condition of proceeding.
How does a membrane warranty affect the fixing method?
It may restrict penetration, require protection mats, or specify who may reinstate the surface. Those terms are obtained in writing before the layout is settled, and any reinstatement obligation during the system's life is allocated in the scope.
What shade analysis is used?
An hourly profile for representative days, set against the load profile. Annual loss percentages hide timing, and the timing decides whether shaded generation falls in hours the site could have used it.