Home / Projects

Projects

Work described in detail.

Six commercial and industrial energy projects, from rooftop generation and battery storage to advisory review and lighting efficiency. Each account sets out the site condition, the investigation, the response and the outcome.

What decided each project

Each project was governed by a site condition identified before equipment was selected: switchboard capacity, roof membrane condition, an export limit at the connection, the timing of demand events, or the absence of an agreed measurement baseline. The size and staging of each installation followed from that condition.

The work spans solar generation, battery storage, staged development, advisory review and the measurement of efficiency measures. These accounts are illustrative examples of the company's method. Client names are not published and no commercial figure is attached to any account. Outcomes are recorded operationally — demand at the meter, self-consumption, continuity of production — and each project states what remains outstanding.

Selected projects

Six sites, six different questions.

The briefs differ in load shape, connection conditions and operating constraints. An array sized for a daytime factory does not suit a warehouse with an export limit, and a battery configured for one duty may be wrong for a site with several.

Solar PV · Industrial premises

01 Moorebank Rooftop Array

A daytime load and an underused roof, held back by an ageing switchboard. The response was a two-stage array with the second stage tied to measured performance.

View project
Battery storage · Cold chain

02 Cold Store Peak Shaving

Compressor restarts after dark were setting the demand peak. A battery originally described as a single-duty asset was given a clear hierarchy of duties instead.

View project
Staged development · Manufacturing

03 Manufacturing Staged Solar

A continuous production line, short shutdown windows and a constrained board. Generation was added in three stages without stopping the line.

View project
Solar and storage · Logistics

04 Warehouse Solar & Storage

A large roof, a modest daytime load and a constrained export connection. The array was sized to the site, not to the available space.

View project
Energy consulting · Corporate

05 Corporate Energy Review

The question was whether to buy plant. An advisory review found tariff and control issues first, and generation was deliberately deferred.

View project
Efficiency · Distribution centre

06 Distribution Centre Lighting

High-bay luminaires running long hours, with a measurement method agreed before any replacement. No generation was added to this site.

View project

At a glance

Six projects, six governing constraints.

The table reduces each project to the condition that mattered most and the response it produced.

ProjectMain constraintResponse
01 Moorebank Rooftop ArrayAn underused roof paired with a switchboard approaching the end of its useful life.Two-stage array; the second stage held back until the first stage had produced measured performance data and the board had been addressed.
02 Cold Store Peak ShavingCompressor restarts after dark setting the demand peak, with several competing duties for one battery.A stated hierarchy of duties for the storage asset, so that peak shaving took priority and did not undermine the other functions.
03 Manufacturing Staged SolarContinuous production, short shutdown windows and a constrained switchboard.Generation introduced in three stages, with connection work aligned to planned outages rather than to a convenient construction programme.
04 Warehouse Solar & StorageLarge roof area but a modest daytime load and a restricted export connection.The array sized to what the site could use and export, rather than to the space available on the roof.
05 Corporate Energy ReviewUnclear whether the underlying issue was plant capacity, tariff structure or control settings.An advisory review of bills and controls first; generation deliberately deferred pending a clearer evidence base.
06 Distribution Centre LightingHigh-bay luminaires running long hours, with no agreed baseline for measuring a change.A measurement method agreed before replacement, then a like-for-like upgrade; no generation added to the site.

How a project starts

From a site question to a written scope.

Every project followed the same sequence. It begins with the question the site brought to the office and ends with a document the client can act on, defer or decline.

01

The brief, as it was presented

A request for generation, a complaint about a peak charge, a need to keep a production line running through an upgrade. The original question is recorded, because the review often changes it.

02

Site evidence

Interval demand records, tariff and connection documents, switchboard condition, roof layout and membrane history, access routes, operating hours and shutdown windows. Measured information is separated from information reported by the client.

03

Options tested

Generate on the roof, reduce the load first, add storage, stage the work, or defer. Each option is advanced or set aside on stated grounds, and the record shows which.

04

The governing constraint

An ageing board with limited spare ways, an export ceiling, a roof warranty, a short maintenance window or a duty a battery must prioritise. The constraint is named before the equipment is selected.

05

Written scope

The scope records the question, the inputs, the assumptions, the options, the exclusions and the outstanding items. Work proceeds only after that document exists and has been accepted.

Selection and reporting

Questions about these accounts.

How projects are chosen for publication, what each account contains, and how outcomes are recorded.

How are projects selected for this page?

Projects are selected to cover distinct technical subjects across the company's solution areas: rooftop generation, battery storage, staged development, combined solar and storage, advisory review and lighting efficiency. Each account is an illustrative example chosen because it demonstrates a specific engineering constraint and the method used to resolve it, not because of its size or commercial value.

Why are client names and locations withheld?

Client identities, street addresses and commercial terms are not published. Sites are described by their operating character — an industrial premises, a refrigerated store, a manufacturing plant, a distribution warehouse — and by the suburb-level region where that is relevant to the technical account. This keeps the engineering content available while protecting the parties involved.

What does each project account contain?

Each account follows the same structure: the brief as presented, the site evidence gathered, the governing constraint, the options considered, the response implemented and the outcome recorded. Inputs such as interval demand data, connection documents, switchboard condition and roof surveys are described where they shaped the design. Exclusions and outstanding items are stated alongside the completed work.

How are outcomes verified and reported?

Outcomes are checked against measured records: generation, grid import, site demand and export read from interval data, with the comparison method agreed before installation. Findings are reported qualitatively — what changed at the meter, whether production continued, what remains outstanding. Dollar figures, percentages and payback claims are not attached to these accounts.

Can a comparable site be discussed with the office?

Yes. The engineers assess a site against the same inputs used in these accounts: interval data, tariff and connection documents, switchboard condition, roof layout and operating hours. An enquiry can be started through the form below, through the quote request page, or by contacting the Moorebank office directly on 02 7201 8622.

Whose projects are these?

Projects delivered from the Moorebank office to Australian commercial and industrial clients. Client names and street addresses are not published; each account states the site condition, the method, the outcome and what remains outstanding.

Why are there no financial results?

A payback or savings figure depends on the site's tariff, load and operating pattern. A figure from another premises does not transfer, and presenting one as typical would mislead. The accounts record operational change, which can be compared; commercial results belong in a written scope for a specific site.

Can my site be compared with one of these?

Partly. Compare the governing constraint first: board capacity, roof condition, export limit, production windows or cold-chain duty. Where that constraint matches, the method is likely to transfer; where it differs, the answer probably will too.

What information would show whether my site is similar?

Interval data for a representative period, the tariff schedule, the board's condition and rating, the roof's type and warranty position, and a note on operating hours. With those five, the office can say whether a comparison is meaningful.

Client comment

On reading a project before commissioning one.

A comment on using project accounts as evidence.

“

Reading the accounts was useful because each one named the constraint first. It made our own constraint obvious.

Operations managerWarehousing, south-west Sydney

Enquiry

Discuss a comparable site

Describe the site and the question. The office responds with the inputs needed to scope a review.